“Access Sacramento Office Update: Cubicles”


 
We are almost to the finish line. This week cubicle walls are going in. The process began last week on Wednesday and we are hoping to see them fully installed by the end of the week. The new Front Desk area will be fresh and clean and welcoming; no more leaning over the tall counter. We will also have a new ‘green room/meeting area’ for our members to use during their productions. 
 
The next steps after the cubicle install include some electronic stuffs including computer lines and phone lines being transferred back into the room. Our goal is to be in there within the next couple weeks.

In the meantime please come visit us for membership information, sign ups, and renewals in our temporary location in the Access Sacramento Media Lab.
 
.