Here are some updates on Access Sacramento’s office renovations.

The “main” office has been cleared of all furniture and is ready to have the new carpet put in and to be painted.    These renovations will begin next week and continue on for the next three or four weeks.

When the office is complete, Membership services and the Programming Department will be back into the freshly painted space.  Approximately 1/3 of the renovated office space will be available for small group meetings and occasional use as a much needed “green room” for our studio productions.

Ron Cooper and Liz Harrison have already moved into the Rough and Ready Room, our new administrative office.

The remaining estimated timeline for these changes is as follows:

-March 12-23 — City staff paints and carpets Office space.

-March 26-March 30 — Move back into Office Membership and Programming Services.

During these exciting but stressful times, we ask for your cooperation and patience. Much is involved, and disruptions will occur but the end result will be worthwhile.